How a project gets into the ground.
Intake and KLIC
We file the KLIC notification and combine every existing cable and pipe into one subsurface model. You see what is in the ground before a single line is designed.
Site-conditions quickscan
We check the area for nature, archaeology, UXO, trees and land ownership. Bottlenecks are on the map, not discovered at the permit stage.
Preliminary design
The first route with crossings, chainage and connections. You approve the PD in the client portal, recorded with name, time and version.
Trial trenches and surveying
Our own crew digs trial trenches and measures actual positions with RTK-GNSS. Here the gas main lies 0.40 m off its KLIC position.
Detailed design and permit
The buildable design: depth, an HDD bore under the road and sewer, and the calculations. A second engineer checks it, then we apply for the permit.
Handover
After installation we survey the cable and deliver the as-built and handover file. One file, with every version and every approval.
Anonymised, but concrete.
Our clients run critical infrastructure. We only show client names, exact locations and drawings with their approval. Regions are given at province level.
- P.012Handed overUtrecht · 2026 · Grid operatorLV grid replacement, Utrecht-OostLV2.4 kmRoute engineering · Trenchless techniques +3
- P.018DDNoord-Brabant · 2026 · Grid operatorMV link to a new substationMV6.8 kmRoute engineering · Trenchless techniques +3
- P.021Handed overGelderland · 2025 · ContractorRural fibre roll-outData14.2 kmRoute engineering · Work preparation +1
- P.009Handed overZuid-Holland · 2025 · Grid operatorGas main diversion at a rail crossingGas0.9 kmTrenchless techniques · Calculations +2
- P.026PDOverijssel · 2026 · Grid operatorDrinking-water transport main, phase 1Water3.2 kmDigital surveying · Trial trenches +1
- P.015Handed overZuid-Holland · 2025 · MunicipalityGrid reinforcement, business parkLVMV1.6 kmRoute engineering · Calculations +2